[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-94174":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},94174,64,2,"多选题","英国NEC合同文本中，关于主要选项条款的说法，错误的有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","选项A适用于承包加酬金合同",true,{"key":16,"text":17,"correct":18},"B","选项B适用于综合单价计量承包",false,{"key":20,"text":21,"correct":18},"C","选项C适用于拟建工程范围在订立合同时还没有完全界定的情况",{"key":23,"text":24,"correct":14},"D","选项E适用于工程范围的界定已经明确的情况",{"key":26,"text":27,"correct":18},"E","选项F适用于施工管理承包","AD","此题考查英国NEC工程施工合同文本结构中主要选项条款。标价合同适用于签订合同时价格已确定的合同，合同文本中选项A适用于固定价格承包，选项B适用于综合单价计量承包；目标合同（合同文本中选项C、选项D）适用于拟建工程范围在订立合同时尚未完全界定或预测风险较大的情形；成本补偿合同（合同文本中选项E）适用于工程范围界定尚不明确，甚至以目标合同为基础也不够充分，而且又要求尽早动工的情形；管理合同（合同文本中选项F）适用于施工管理承包。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]