[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-94144":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},94144,64,2,"多选题","房地产开发项目可行性研究报告中，需要编制开发建设计划，其中前期开发计划包括( )。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","项目创意",true,{"key":16,"text":17,"correct":14},"B","可行性研究",{"key":19,"text":20,"correct":14},"C","获取开工许可证",{"key":22,"text":23,"correct":24},"D","单项工程开工时间",false,{"key":26,"text":27,"correct":24},"E","单项工程竣工时间","ABC","此题考查可行性研究报告中的开发建设计划编制。开发建设计划编制包括以下内容。①前期开发计划。包括从项目创意、可行性研究、下达规划任务、征地拆迁、委托规划设计、取得开工许可证直至完成开工前准备等一系列工作计划。②工程建设计划。包括各个单项工程的开竣工时间、进度安排、市政工程配套建设计划。③建设场地的布置。④施工队伍的选择。选项D、E属于工程建设计划编制的内容。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]