[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-94116":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},94116,64,2,"多选题","施工过程中承包人向发包人索赔时，下列可以获得赔偿的方式有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","延长工期",true,{"key":16,"text":17,"correct":18},"B","缩短工期",false,{"key":20,"text":21,"correct":14},"C","发包人支付实际发生的额外费用",{"key":23,"text":24,"correct":14},"D","发包人支付合理的预期利润",{"key":26,"text":27,"correct":14},"E","发包人按合同的约定支付违约金","ACDE","施工过程中承包人索赔时，可以选择下列一项或几项方式获得赔偿：①延长工期；②发包人支付实际发生的额外费用；③发包人支付合理的预期利润；④发包人按合同的约定支付违约金。当承包人的费用索赔与工期索赔要求相关联时，发包人在做出费用索赔的批准决定时，应结合工程延期，综合做出费用赔偿和工程延期的决定。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]