[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-94115":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},94115,64,2,"多选题","当承包人提出索赔时，其可以选择的赔偿方式有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","要求发包人支付实际发生的额外费用",true,{"key":16,"text":17,"correct":14},"B","要求发包人支付合理的预期利润",{"key":19,"text":20,"correct":14},"C","要求延长建设工期",{"key":22,"text":23,"correct":24},"D","要求发包人进行工程变更",false,{"key":26,"text":27,"correct":14},"E","要求发包人按合同的约定支付违约金","ABCE","施工过程中承包人索赔时，可以选择下列一项或几项方式获得赔偿：①延长工期；②发包人支付实际发生的额外费用；③发包人支付合理的预期利润；④发包人按合同的约定支付违约金。当承包人的费用索赔与工期索赔要求相关联时，发包人在做出费用索赔的批准决定时，应结合工程延期，综合做出费用赔偿和工程延期的决定。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]