[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-94104":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},94104,64,2,"多选题","下列关于建筑安装工程不可调值总价合同的说法，错误的有（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","采用这种合同，承包商只承担了实物工程量、成本和工期等因素的风险",true,{"key":16,"text":17,"correct":18},"B","采用这种合同，承包方承担了通货膨胀风险",false,{"key":20,"text":21,"correct":14},"C","通常适用于工程规模较大、技术复杂的大中型建筑安装工程",{"key":23,"text":24,"correct":18},"D","通常适用于工期较短、工期在一年以内的建筑安装工程",{"key":26,"text":27,"correct":14},"E","通常适用于工期在一年以上的建筑安装工程","ACE","不可调值总价合同承包方承担的风险较大，如物价波动、地质条件不利、气候条件恶劣等，因此价格中应考虑风险因素，合同价格一般会高些。通常适用 于工期较短(如一年以内)的项目。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]