[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-94096":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},94096,64,2,"多选题","根据《建设工程工程量清单计价规范》，不属于分部分项工程综合单价所包含内容的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","利润",false,{"key":16,"text":17,"correct":18},"B","规费",true,{"key":20,"text":21,"correct":18},"C","措施费",{"key":23,"text":24,"correct":14},"D","企业管理费",{"key":26,"text":27,"correct":14},"E","一定范围内的风险费用","BC","本题考查分部分项工程综合单价。分部分项工程综合单价应包括：人工费、材料费、机械使用费、管理费、利润、风险因素。而规费、措施费与分部分项工程费并列列项，不包含其中。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]