[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-94092":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},94092,64,2,"多选题","根据现行规定，关于工程预付款的说法错误的有（）",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工程预付款百分比应在合同中约定",false,{"key":16,"text":17,"correct":14},"B","包工包料工程的预付款比例不得低于合同金额的10％",{"key":19,"text":20,"correct":21},"C","工程开工后，已支付的预付款必须在工程竣工结算时一次性扣回",true,{"key":23,"text":24,"correct":21},"D","在具备施工条件的前提下，发包人应在双方签订合同后的1个月内或不迟于约定开工日期前的1个月内预付工程款",{"key":26,"text":27,"correct":21},"E","工程预付款应在竣工决算时予以扣回","CDE","工程预付款应按照合同条款中约定的时间、数额和比例，将已支付的预付款以抵充各期工程进度款的方式陆续扣回，直到扣回的金额达到合同约定的预付款金额为止．故选项C、E错误；选项D的错误在于：在具备施工条件的前提下，发包人应在双方签订合同后的一个月内或不迟于约定开工日期前的7天内预付工程款，而不是开工前的1个月内。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]