[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-94073":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},94073,64,2,"多选题","工程量清单计价的工程造价应由（）组成。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","间接费",false,{"key":16,"text":17,"correct":18},"B","措施项目费",true,{"key":20,"text":21,"correct":18},"C","其他项目费",{"key":23,"text":24,"correct":18},"D","规费和税金",{"key":26,"text":27,"correct":18},"E","分部分项工程费","BCDE","工程量清单计价的工程造价由分部分项工程费(含利润)、措施项目费、其他项目费、规费和税金组成。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]