[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-94066":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},94066,64,2,"多选题","根据《建设工程工程量清单计价规范》，下列事项中，会导致发承包双方按照合同约定调整合同价款的有( )。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","出现不可抗力事件",true,{"key":16,"text":17,"correct":14},"B","合同履行过程中发生法律法规变化",{"key":19,"text":20,"correct":14},"C","工程量清单中项目特征描述与实际施工设计图纸不符",{"key":22,"text":23,"correct":24},"D","未经发包人确认的施工方案调整",false,{"key":26,"text":27,"correct":14},"E","设计图纸修改引起的工程变更","ABCE","此题考查合同价款调整情形。在合同履行期间，若发生法律法规变化、工程变更、项目特征描述不符、工程量清单缺项、工程量偏差、物价变化、不可抗力、提前竣工(赶工补偿)、工程索赔等事项，发承包双方应当按照合同约定调整合同价款。经发承包双方确认的合同价款调整，作为追加(减)合同价款，应与工程进度款同期支付。如在工程结算期间发生合同价款调整，应在竣工结算款中支付。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]