[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-94062":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},94062,64,2,"多选题","工程量清单中的其他项目清单内容包括( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","规费",false,{"key":16,"text":17,"correct":14},"B","税金",{"key":19,"text":20,"correct":21},"C","总承包服务费",true,{"key":23,"text":24,"correct":21},"D","暂列金额",{"key":26,"text":27,"correct":21},"E","暂估价","CDE","此题考查其他项目清单内容。其他项目清单是指分部分项工程项目清单、措施项目清单所包含的内容以外，因招标人的特殊要求而发生的与拟建工程有关的其他费用项目和相应数量的清单。其他项目清单应按照下列内容列项：暂列金额、暂估价、计日工和总承包服务费。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]