[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-94055":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},94055,64,2,"多选题","建设投资包括（ ）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工程费用",true,{"key":16,"text":17,"correct":18},"B","建设期利息",false,{"key":20,"text":21,"correct":14},"C","工程建设其他费用",{"key":23,"text":24,"correct":14},"D","基本预备费",{"key":26,"text":27,"correct":14},"E","涨价预备费","ACDE","建设投资包括工程费用、工程建设其他费用、预备费",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]