[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-94054":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},94054,64,2,"多选题","涨价预备费的计算基数包括( )。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","建筑安装工程费",true,{"key":16,"text":17,"correct":14},"B","设备及工器具购置费",{"key":19,"text":20,"correct":14},"C","工程建设其他费用",{"key":22,"text":23,"correct":14},"D","基本预备费",{"key":25,"text":26,"correct":27},"E","建设期利息",false,"ABCD","此题考查涨价预备费计算基数。涨价预备费一般是根据国家规定的投资综合价格指数，按估算年份价格水平的投资额为基数，采用复利方式计算。建设期第t年投资计划额，包括：工程费用、工程建设其他费用及基本预备费，即第t年静态投资计划额。其中，工程费用是指建设期直接用于工程建造、设备购置及安装的费用，包括设备及工器具购置费和建筑安装工程费。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]