[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-94045":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},94045,64,2,"多选题","下列费用中，属于工程建设其他费用的有( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","设备运杂费",false,{"key":16,"text":17,"correct":14},"B","企业管理费",{"key":19,"text":20,"correct":21},"C","勘察设计费",true,{"key":23,"text":24,"correct":21},"D","技术引进费",{"key":26,"text":27,"correct":21},"E","联合试运转费","CDE","此题考查工程建设其他费用构成。工程建设其他费用可分为三类，即土地使用费和其他补偿费、与工程建设过程有关的费用、与工程未来生产经营有关的费用。选项C、D属于与工程建设过程有关的费用，选项E属于与工程未来生产经营有关的费用。选项A属于设备及工器具购置费。选项B属于建筑安装工程费。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]