[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-94043":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},94043,64,2,"多选题","当工程网络计划实施中产生的进度偏差影响到总工期，且有关工作的逻辑关系允许改变时，可以有效缩短工期的方法有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","顺序进行的工作改为平行作业",true,{"key":16,"text":17,"correct":14},"B","顺序进行的工作改为搭接作业",{"key":19,"text":20,"correct":21},"C","保持顺序进行的作业，提高工作效率",false,{"key":23,"text":24,"correct":14},"D","分段组织流水作业",{"key":26,"text":27,"correct":21},"E","增大工作之间的间歇时间","ABD","当工程网络计划实施中产生的进度偏差影响到总工期，且有关工作的逻辑关系允许改变时，可以改变关键线路和超过计划工期的非关键线路上的有关工作之间的逻辑关系，达到缩短工期的目的。例如，将顺序进行的工作改为平行作业、搭接作业或分段组织流水作业等，都可以有效地缩短工期。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]