[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-94035":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},94035,64,2,"多选题","调整网络计划非关键工作时差的方法是（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","将工作在其最早开始时间和最早完成时间范围内移动",false,{"key":16,"text":17,"correct":18},"B","将工作在其最早开始时间和最迟完成时间范围内移动",true,{"key":20,"text":21,"correct":18},"C","延长工作的持续时间",{"key":23,"text":24,"correct":18},"D","缩短工作的持续时间",{"key":26,"text":27,"correct":14},"E","将工作断开，分段完成","BCD","非关键工作时差的调整应在其拥有的时差范围内进行，以便更充分地利用资源、降低工程成本或满足工程施工的需要。调整方法如下： (1)应在其拥有的时差范围内进行调整，并重新计算时间参数 (2)工作可以在最早开始时问与最迟完成时间范围内变动 (3)延长或缩短工作的持续时间",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]