[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-94033":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},94033,64,2,"多选题","网络计划实施中的控制主要包括（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","检查并掌握工程的实际进展情况",true,{"key":16,"text":17,"correct":18},"B","掌握工程成本的控制情况",false,{"key":20,"text":21,"correct":14},"C","分析产生进度偏差的主要原因",{"key":23,"text":24,"correct":14},"D","确定相应的纠偏措施或调整方法",{"key":26,"text":27,"correct":18},"E","保证项目按照合同要求的工期按时完工","ACD","本题考查网络计划实施中的控制的主要内容。网络计划实施中的控制主要内容为：检查并掌握工程的实际进展情况，将工程实际进度与网络计划进行比较分析，对产生进度偏差的原因及其对工期和后续工作的影响进行分析，确定相应的纠偏措施或调整方法。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]