[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-94032":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},94032,64,2,"多选题","网络计划中关键线路的确定需要具备的条件是（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","具有关键节点",false,{"key":16,"text":17,"correct":14},"B","具有总时差为零的工作",{"key":19,"text":20,"correct":14},"C","具有自由时差为零的工作",{"key":22,"text":23,"correct":24},"D","贯穿起点和终点的均是总时差最小的工作",true,{"key":26,"text":27,"correct":24},"E","所有工作之间的时间间隔均为零","DE","本题考查网络计划中关键线路确定需要具备的条件。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]