[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-94031":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},94031,64,2,"多选题","网络计划调整时，非关键工作在其时差范围内进行调整的目的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","更充分地利用资源",true,{"key":16,"text":17,"correct":18},"B","缩短非关键工作的持续时间",false,{"key":20,"text":21,"correct":14},"C","降低工程成本",{"key":23,"text":24,"correct":14},"D","满足工程施工的需要",{"key":26,"text":27,"correct":18},"E","缩短项目的总工期","ACD","本题考查网络计划调整。网络计划调整时，非关键工作在其时差范围内进行调整的目的：更充分地利用资源、降低工程成本和满足工程施工的需要。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]