[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-94029":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},94029,64,2,"多选题","某单代号网络计划中，工作B的最早开始时间为第8周，持续时间为6周。其两项紧后工作D和G的最早开始时间分别为第16周和第18周，工作D和G的总时差分别为3周和2周，则工作B的（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","总时差为5周",true,{"key":16,"text":17,"correct":18},"B","总时差为6周",false,{"key":20,"text":21,"correct":14},"C","自由时差为2周",{"key":23,"text":24,"correct":18},"D","自由时差为4周",{"key":26,"text":27,"correct":14},"E","最迟完成时间为第19周","ACE","(1)工作B的最早完成时间：8+6=14(周)。 (2)工作B与D、G的时间间隔分别：16—14=2(周)；18—14=4(周)。 (3)工作B的自由时差：Min(2，4)=2(周)。 (4)工作B的总时差：Min(2+3，4+2)=5(周)。 (5)工作B的最迟完成时间：最早完成时间+总时差=14+5=19(周)。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]