[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-94028":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},94028,64,2,"多选题","在网络计划实施中，当实际进度比计划进度拖后或提前时，调整网络计划的方法有（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","调整进度前锋线",false,{"key":16,"text":17,"correct":18},"B","调整资源的投入",true,{"key":20,"text":21,"correct":14},"C","调整工作的最早开始时间",{"key":23,"text":24,"correct":18},"D","调整工作之间的逻辑关系",{"key":26,"text":27,"correct":18},"E","增、减工作项目","BDE","本题考查的是调整网络计划的方法，共六种，分别是：①调整关键线路：②调整非关键工作时差；③增、减工作项目；④调整工作之间的逻辑关系；⑤调整工作的持续时间：⑥调整资源的投入。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]