[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-94026":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},94026,64,2,"多选题","某工程网络计划中，已知工作M的自由时差为4天，在该网络计划的执行过程中发现工作M的持续时间比原计划延长了2天而其他工作正常，则此时工作M（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","不会使总工期延长",true,{"key":16,"text":17,"correct":14},"B","不影响其后续工作的正常进行",{"key":19,"text":20,"correct":21},"C","总时差不变．自由时差减少2天",false,{"key":23,"text":24,"correct":14},"D","总时差和自由时差各减少2天",{"key":26,"text":27,"correct":21},"E","自由时差不变．总时差减少2天","ABD","总时差大于或等于自由时差，因此总时差大于或等于4天。如M>A或M>B，则对总工期推后M-A，使紧后工作的最早开始时间推后M-B。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]