[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-94024":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},94024,64,2,"多选题","某单代号网络计划中，工作H与其紧后工作K和M的时间间隔分别为3周和6周．工作K和M的总时差分别为5周和3周，下列关于该网络计划时间参数的说法中，正确的为（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工作K和M的时间间隔为3周",false,{"key":16,"text":17,"correct":14},"B","工作M的自由时差为9周",{"key":19,"text":20,"correct":21},"C","工作H的总时差为8周",true,{"key":23,"text":24,"correct":21},"D","工作H的自由时差为3周",{"key":26,"text":27,"correct":14},"E","工作K的自由时差为8周","CD","选项A不对。题目中没有说明K、M之间的逻辑关系，所以无法判断这两项工作的时间间隔。选项B不对。因为自由时差小于或等于总时差，M的总时差题目中给出为3周，所以它的自由时差不可能是9周．大于总时差3周。选项C正确。在单代号网络计划中，工作的总时差=Min{与紧后工作的时间问隔+对应紧后工作的总时差}=Min{(3+5)，(6+3)}=8。选项D正确。自由时差为与紧后工作时间间隔的最小值。选项E错误。原因同B。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]