[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-94015":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},94015,64,2,"多选题","在绘制网络图时，表示箭线交叉的方法有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","过桥法",true,{"key":16,"text":17,"correct":18},"B","母线法",false,{"key":20,"text":21,"correct":18},"C","分段法",{"key":23,"text":24,"correct":14},"D","指向法",{"key":26,"text":27,"correct":18},"E","流水法","AD","此题考查双代号网络计划绘制规则。双代号网络计划绘制时应尽量避免网络图中工作箭线的交叉。当交叉不可避免时，可以采用过桥法或指向法处理。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]