[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-94014":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},94014,64,2,"多选题","在绘制双代号网络图时，应遵循的基本规则有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","双代号网络图必须正确表达已定的逻辑关系",true,{"key":16,"text":17,"correct":18},"B","双代号网络图中，可以出现循环回路",false,{"key":20,"text":21,"correct":14},"C","双代号网络图中，在节点之间严禁出现带双向箭头或无箭头的连线",{"key":23,"text":24,"correct":18},"D","网络图中的节点都必须有编号，其编号可以重复",{"key":26,"text":27,"correct":14},"E","双代号网络图中，严禁出现没有箭头节点或没有箭尾节点的箭线","ACE","此题考查双代号网络图绘图规则。网络图必须按照已定的逻辑关系绘制，故选项A正确。网络图中严禁出现从一个节点出发，顺箭头方向又回到原出发点的循环回路。如果出现循环回路，会造成逻辑关系混乱，使工作无法按顺序进行。故选项B错误。网络图中严禁出现双向箭头和无箭头的连线。否则，工作进行的方向不明确，因而不能达到网络图有向的要求。故选项C正确。网络图中的节点都必须有编号，其编号严禁重复，并应使每一条箭线上箭尾节点编号小于箭头节点编号，故选项D错误。网络图中严禁出现没有箭尾节点的箭线和没有箭头节点的箭线，故选项E正确。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]