[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-94006":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},94006,64,2,"多选题","下列监理人员的职责中，属于总监理工程师不得将其委托给总监理工程师代表的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","组织召开监理例会",false,{"key":16,"text":17,"correct":14},"B","组织审查和处理工程变更",{"key":19,"text":20,"correct":21},"C","组织编制监理规划",true,{"key":23,"text":24,"correct":21},"D","签发开工令和复工令",{"key":26,"text":27,"correct":21},"E","组织审查施工组织设计","CDE","总监理工程师不得将下列工作委托给总监理工程师代表：①组织编制监理规划，审批监理实施细则；②根据工程进展及监理工作情况调配监理人员；③组织审查施工组织设计、（专项）施工方案；④签发工程开工令、暂停令和复工令；⑤签发工程款支付证书，组织审核竣工结算；⑥调解建设单位与施工单位的合同争议，处理工程索赔；⑦审查施工单位的竣工申请，组织工程竣工预验收，组织编写工程质量评估报告，参与工程竣工验收；⑧参与或配合工程质量安全事故的调查和处理。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]