[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93996":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},93996,64,2,"多选题","对建设工程进度进行全方位控制时，应做到（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","对建设工程所有工程内容的进度都要进行控制",true,{"key":16,"text":17,"correct":14},"B","对建设工程所有工作内容的进度都要进行控制",{"key":19,"text":20,"correct":21},"C","在确定进度目标时，不能对投资和质量目标产生影响",false,{"key":23,"text":24,"correct":21},"D","在编制进度计划时，应将各阶段工作内容进行充分搭接",{"key":26,"text":27,"correct":14},"E","对影响进度的各种因素都要进行控制","ABE","对建设工程进度进行全方位控制时，包括以下四个方面内容： (1)对建设工程所有工程内容的进度都要进行控制。 (2)对建设工程所有工作内容的进度都要进行控制。 (3)对影响进度的各种因素都要进行控制。 (4)控制各方面工作进度对施工进度的影响。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]