[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93989":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},93989,64,2,"多选题","监理实施细则应依据（ ）进行编制。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","委托方要求",false,{"key":16,"text":17,"correct":18},"B","已批准的监理规划",true,{"key":20,"text":21,"correct":14},"C","监理工作制度",{"key":23,"text":24,"correct":18},"D","与专业工程相关的标准、设计文件和技术资料",{"key":26,"text":27,"correct":18},"E","施工组织设计、(专项）施工方案","BDE","监理实施细则应依据下列内容编制。 (1)已批准的监理规划。 (2)与专业工程相关的标准、设计文件和技术资料。 (3)施工组织设计、(专项）施工方案。 此外，监理实施细则的编制还可依据工程监理单位的规章制度和经认证发布的质量管理体系，以达到监理内容的全面、完整，有效地提高工程监理工作质量。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]