[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93942":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},93942,64,2,"多选题","下列风险中，属于业主或开发商在项目实施阶段风险的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","项目产品需求变化",false,{"key":16,"text":17,"correct":14},"B","内部决策机制风险",{"key":19,"text":20,"correct":21},"C","监理工程师失职风险",true,{"key":23,"text":24,"correct":21},"D","承包商缺乏合作诚意",{"key":26,"text":27,"correct":21},"E","合同条款不严谨","CDE","由于项目实施阶段涉及范围广、参与者众多、过程复杂等原因，业主或开发商会面临更多风险，主要包括：①政府或主管部门对工程项目干预太多；②勘察设计工作不到位；③合同条款不严谨；④承包商缺乏合作诚意；⑤监理工程师失职；⑥材料或设备供应商履约不力。AB两项属于项目决策阶段的风险。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]