[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93900":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},93900,64,2,"多选题","工程风险事件造成的损失通常包括( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","供应链短缺",false,{"key":16,"text":17,"correct":18},"B","费用超支",true,{"key":20,"text":21,"correct":18},"C","工期拖延",{"key":23,"text":24,"correct":18},"D","质量事故",{"key":26,"text":27,"correct":18},"E","安全事故","BCDE","此题考查工程风险损失估计。工程风险事件造成的损失通常包括：费用超支、进度（工期）拖延、质量事故、安全事故四方面。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]