[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93897":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},93897,64,2,"多选题","下列建设工程实施过程发生的事件中，属于业主或开发商在项目实施阶段风险的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","文化水平会影响居民对项目的需求层次",false,{"key":16,"text":17,"correct":18},"B","勘察设计工作不到位",true,{"key":20,"text":21,"correct":14},"C","投资决策组织机制不健全带来的内部决策机制风险",{"key":23,"text":24,"correct":18},"D","承包商缺乏合作诚意",{"key":26,"text":27,"correct":18},"E","材料或设备供应商履约不力","BDE","此题考查业主或开发商风险。项目实施阶段，由于涉及范围广、参与者众多、过程复杂等原因，业主或开发商会面临更多风险，包括政府或主管部门对工程项目干预太多，勘察设计工作不到位，合同条款不严谨，承包商缺乏合作诚意，监理工程师失职，材料或设备供应商履约不力等风险。选项A、C风险属于业主或开发商在项目决策阶段的风险。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]