[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93893":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},93893,64,2,"多选题","风险可根据不同原则和标准进行分类，按风险发生的原因可将风险分为( )。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","自然风险",true,{"key":16,"text":17,"correct":14},"B","社会风险",{"key":19,"text":20,"correct":14},"C","政治风险",{"key":22,"text":23,"correct":24},"D","责任风险",false,{"key":26,"text":27,"correct":14},"E","经济风险","ABCE","此题考查工程风险分类。工程风险是指工程项目在决策、设计、施工及竣工验收等阶段可能遭受的风险。为便于识别风险和对不同类型风险采取不同的分析方法和应对措施，可按不同原则和标准，对工程风险进行分类。其中，按风险发生的原因可以分为自然风险、政治风险、社会风险、经济风险和金融风险。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]