[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93864":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},93864,64,2,"多选题","BIM 5D模型包括的内容有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","设施管理应用",false,{"key":16,"text":17,"correct":18},"B","建筑构件信息",true,{"key":20,"text":21,"correct":18},"C","进度信息",{"key":23,"text":24,"correct":18},"D","WBS信息",{"key":26,"text":27,"correct":18},"E","预算信息","BCDE","此题考查BIM 5D包含内容。3D信息模型与预算模型、进度计划集成扩展成为BIM 5D模型。BIM 5D模型包括建筑构件信息、进度信息、WBS信息、预算信息及其相互关联关系。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]