[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93863":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},93863,64,2,"多选题","基于建筑信息模型（BIM)技术的施工进度计划编制流程的主要步骤有（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","WBS施工任务分解",true,{"key":16,"text":17,"correct":14},"B","施工进度计划任务包",{"key":19,"text":20,"correct":21},"C","执行过程计价",false,{"key":23,"text":24,"correct":14},"D","数据接口集成",{"key":26,"text":27,"correct":14},"E","形成4D进度计划","ABDE","此题考查基于BIM的施工进度计划编制流程。基于BIM的施工进度计划编制，第一步是建立工作分解结构（WBS)，然后将WBS作业进度、资源等信息与BIM模型图元信息链接，即可实现4D进度计划，其中的关键是数据接口集成。基于BIM的施工进度计划编制流程如下 选项C执行过程计价属于基于BIM的工程造价管理流程中。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]