[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93803":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},93803,64,2,"多选题","装配式建筑原则上应采用工程总承包模式，对工程总承包单位的要求有( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","相应的项目管理体系",true,{"key":16,"text":17,"correct":14},"B","项目管理能力",{"key":19,"text":20,"correct":21},"C","组织营销能力",false,{"key":23,"text":24,"correct":14},"D","财务和风险承担能力",{"key":26,"text":27,"correct":14},"E","与发包工程相类似的设计、施工或者工程总承包业绩","ABDE","此题考查装配式建筑对工程总承包单位的要求。工程总承包单位应当同时具有与工程规模相适应的工程设计资质和施工资质，或者由具有相应资质的设计单位和施工单位组成联合体。工程总承包单位应当具有相应的项目管理体系和项目管理能力、财务和风险承担能力，以及与发包工程相类似的设计、施工或者工程总承包业绩。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]