[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93788":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},93788,64,2,"多选题","相比传统现浇方式，造成装配式混凝土建筑工程建造方式成本增加的因素有（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","预制构配件的运输费用",true,{"key":16,"text":17,"correct":14},"B","预制构配件的吊装费用",{"key":19,"text":20,"correct":21},"C","钢筋和混凝土工程费用",false,{"key":23,"text":24,"correct":14},"D","大型机械设备的租赁费用",{"key":26,"text":27,"correct":14},"E","拼缝处理及相关材料费用","ABDE","相比传统现浇方式，造成装配式混凝土建筑工程建造方式成本增加的因素有预制构件产品和运输费用、预制构件吊装费用、机械费、大型机械设备的租赁费用、墙板和楼板拼缝处理及相关材料费用。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]