[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93787":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},93787,64,2,"多选题","装配式混凝土建筑工程成本与传统现浇方式相比减少的有（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","机械费",false,{"key":16,"text":17,"correct":18},"B","砌筑工程费",true,{"key":20,"text":21,"correct":18},"C","措施费",{"key":23,"text":24,"correct":14},"D","墙板和楼板拼缝处理及相关材料费",{"key":26,"text":27,"correct":18},"E","钢筋工程费","BCE","装配式混凝土建筑工程成本与传统现浇方式相比减少的有钢筋工程费、混凝土工程费、砌筑工程费、措施费、抹灰工程费。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]