[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93780":3},{"question":4,"library":25},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":23,"analysis":24},93780,64,2,"多选题","引发装配式混凝土建筑工程增量成本的原因有（ ）。 A.预制构件相对传统现浇做法费用有所提高 B.预制构件生产未实现规模效益 C.运输效率不足导致运输费用较高 D.人工工资过高导致成本增加",[11,14,16,18,21],{"key":12,"text":12,"correct":13},"A",true,{"key":15,"text":15,"correct":13},"B",{"key":17,"text":17,"correct":13},"C",{"key":19,"text":19,"correct":20},"D",false,{"key":22,"text":22,"correct":20},"E","ABC","本题考查有关预制构件生产和安装方面因素对费用的影响：①预制构件相对传统现浇做法费用有所提高，②预制构件生产未实现规模效益，③运输效率不足导致运输费用较高。",{"id":6,"name":26,"category":27,"favorite":28},"(中级) 建筑与房地产经济","经济金融",0]