[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93653":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},93653,64,2,"多选题","下列建设工程项目目标控制措施中，属于主动控制的有( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","对项目实施过程进行跟踪、测试、检查，发现异常情况及时采取纠偏措施",false,{"key":16,"text":17,"correct":14},"B","明确项目管理组织中过程控制人员的职责，发现情况及时采取措施进行处理",{"key":19,"text":20,"correct":21},"C","分析影响项目目标和计划实施的各种因素，并将其融入到计划及管理职能之中",true,{"key":23,"text":24,"correct":21},"D","识别风险，在项目计划实施过程中做好风险管理工作",{"key":26,"text":27,"correct":21},"E","制定必要的备用方案，以应对可能出现的影响目标或计划实现的情况","CDE","AB属于被动控制措施。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]