[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93652":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},93652,64,2,"多选题","建设项目的基本目标是对（ ）进行有效控制。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","建设工期",true,{"key":16,"text":17,"correct":14},"B","项目投资",{"key":19,"text":20,"correct":14},"C","工程质量",{"key":22,"text":23,"correct":24},"D","安全生产",false,{"key":26,"text":27,"correct":24},"E","项目风险","ABC","建设项目的基本目标是对建设工期、项目投资和工程质量进行有效控制，这三大目标是一个统一体，即项目管理里面的进度、成本和质量三大目标。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]