[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93633":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},93633,64,2,"多选题","下列风险中，应由业主或投资商承担的有( )。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","市场物价不正常上涨造成建设项目的决算大大超过预算",true,{"key":16,"text":17,"correct":14},"B","恶劣的自然条件造成工程成本增加",{"key":19,"text":20,"correct":14},"C","因战争造成建设项目的损毁",{"key":22,"text":23,"correct":24},"D","因承包商报价失误给投资商带来的额外收入",false,{"key":26,"text":27,"correct":14},"E","因主管部门设置障碍导致工程延期给投资商造成的损失","ABCE","本题考查的是对业主或投资商的风险的理解。业主或投资商通常遇到的风险可归纳为四种：人为风险、经济风险、自然风险和特殊风险。选项A属于经济风险；选项B属于自然风险；选项C属于特殊风险；选项E属于人为风险；选项D属于承包商决策错误风险之一，因此不选。答案为ABCE",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]