[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93623":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},93623,64,2,"多选题","网络图中，关键工作是（ ）的工作。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","自由时差为零",false,{"key":16,"text":17,"correct":18},"B","总时差最小",true,{"key":20,"text":21,"correct":14},"C","时标网络图中无波形线",{"key":23,"text":24,"correct":18},"D","最迟开始时间与最早开始时间差值最小",{"key":26,"text":27,"correct":14},"E","时间间隔为零","BD","在双代号网络计划中，工作总时差最小的工作是关键工作。总时差等于其最迟开始时间减去最早开始时间，或等于最迟完成时间减去最早完成时间。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]