[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93620":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},93620,64,2,"多选题","在工程网络计划中，判断其关键工作与关键线路的方法有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","自由时差为零的工作是关键工作",false,{"key":16,"text":17,"correct":18},"B","总时差最小的工作是关键工作",true,{"key":20,"text":21,"correct":14},"C","双代号网络计划中无虚箭线的线路是关键线路",{"key":23,"text":24,"correct":14},"D","双代号网络计划中由关键节点连成的线路是关键线路",{"key":26,"text":27,"correct":18},"E","单代号网络计划中由关键节点连成，且其时间间隔均为零的线路是关键线路","BE","双代号网络计划中，关键线路是自始至终全部由关键工作组成的线路为关键线路，或线路上总的工作持续时间最长的线路。单代号网络计划中，关键线路是从起点节点开始到终点节点均为关键工作，且所有工作之间的时间间隔均为零的线路。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]