[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93613":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},93613,64,2,"多选题","下列关于建筑安装工程可调值总价合同的说法中，正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","发包方承担了通货膨胀这一不可预测费用因素的风险",true,{"key":16,"text":17,"correct":18},"B","采用这种合同，承包方承担了通货膨胀风险",false,{"key":20,"text":21,"correct":14},"C","通常适用于工期在一年以上的建筑安装工程",{"key":23,"text":24,"correct":18},"D","通常适用于工期较短，工期在一年以内的建筑安装工程",{"key":26,"text":27,"correct":14},"E","采用这种合同，承包商承担了实物工程量、成本和工期等因素的风险","ACE","",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]