[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93611":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},93611,64,2,"多选题","根据《建设工程工程量清单计价规范》(GB50500--2008)，下列建设项目中，必须采用工程量清单计价的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","国有资金占投资总额50%以上的建设项目",true,{"key":16,"text":17,"correct":14},"B","国有资金占投资总额不足50%，但国有投资者实质上拥有控股权的建设项目",{"key":19,"text":20,"correct":21},"C","全部使用外资的建设项目",false,{"key":23,"text":24,"correct":14},"D","全部使用国有资金投资的建设项目",{"key":26,"text":27,"correct":21},"E","全部使用自有资金的建设项目","ABD","本题考核的是工程量清单计价。全部使用国有资金投资或者国有资金投资为主的工程建设项目，必须采用工程量清单计价。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]