[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93602":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},93602,64,2,"多选题","人工工日消耗量中的其他用工包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","超运距用工",true,{"key":16,"text":17,"correct":18},"B","人工幅度差",false,{"key":20,"text":21,"correct":18},"C","基本用工",{"key":23,"text":24,"correct":14},"D","辅助用工",{"key":26,"text":27,"correct":18},"E","非定额用工","AD","考察人工工日消耗量的确定。人工工日消耗量由基本用工、其他用工、预算定额与施工劳动定额的差额组成。其中其它用工包括超运距用工和辅助用工两类。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]