[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93601":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},93601,64,2,"多选题","根据《建设工程工程量清单计价规范》（GB 50500-2008），工程量清单中除了应包括分部分项工程量清单、措施项目清单、其他项目清单外，还应包括( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","单位工程量清单",false,{"key":16,"text":17,"correct":14},"B","单项工程量清单",{"key":19,"text":20,"correct":21},"C","规费项目清单",true,{"key":23,"text":24,"correct":21},"D","税金项目清单",{"key":26,"text":27,"correct":14},"E","预备费项目清单","CD","根据《建设工程工程量清单计价规范》（GB 50500-2008），工程量清单中应包括分部分项工程量清单、措施项目清单、其他项目清单、规费项目清单和税金项目清单五部分。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]