[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93561":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},93561,64,2,"多选题","BIM技术的进度管理流程主要包括（ ） 。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","进度计划编制",true,{"key":16,"text":17,"correct":14},"B","4D模型建立",{"key":19,"text":20,"correct":14},"C","施工进度模拟",{"key":22,"text":23,"correct":14},"D","施工进度控制与分析",{"key":25,"text":26,"correct":27},"E","3D模型建立",false,"ABCD","BIM技术的进度管理流程主要包括：进度计划编制、 4D模型建立、施工进度模拟、施工进度控制与分析。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]