[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93558":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},93558,64,2,"多选题","装配式混凝土建筑工程成本相比较传统现浇方式减少的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","机械费",false,{"key":16,"text":17,"correct":18},"B","砌筑工程费",true,{"key":20,"text":21,"correct":18},"C","措施费",{"key":23,"text":24,"correct":14},"D","墙板和楼板拼缝处理及相关材料费",{"key":26,"text":27,"correct":18},"E","抹灰工程","BCE","装配式混凝土建筑工程成本相比较传统现浇方式减少的有钢筋工程和混凝土工程、砌筑工程、措施费、抹灰工程。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]