[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93552":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},93552,64,2,"多选题","建设项目国民经济评价的内容主要有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","识别国民经济效益与费用",true,{"key":16,"text":17,"correct":18},"B","考察项目的赢利能力和偿债能力",false,{"key":20,"text":21,"correct":14},"C","计算国民经济评价指标并进行方案比选",{"key":23,"text":24,"correct":14},"D","计算和选取影子价格",{"key":26,"text":27,"correct":18},"E","计算投资方案抗风险能力的大小","ACD","国民经济评价是从国家整体角度考察项目的效益和费用，用影子价格、影子工资、影子汇率和社会折现率等，计算项目给国民经济带来的净效益，评价项目经济上的合理性。进行国民经济评价时可以在财务评价的基础上进行，也可以直接进行。直接做国民经济评价的项目，首先应识别和计算项目的直接效益、间接效益、直接费用和间接费用，并在此基础上计算项目的国民经济评价指标。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]