[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93533":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},93533,64,1,"单选题","某建设项目的内部收益率计算采用插值法试算，当i1=15时，净现值为150万元；当i2=18％时，净现值为30万元；当i3=20％时，净现值为-10万元，则该项目的内部收益率为（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","21．50％",false,{"key":16,"text":17,"correct":18},"B","19．50％",true,{"key":20,"text":21,"correct":14},"C","18．38％",{"key":23,"text":24,"correct":14},"D","17．50％","本题考查插值法求内部收益率。内部收益率是指方案寿命期内使用现金流的净现值等于零时的利率。插值法求内部收益率的公式为： 则该项目的内部收益率为r=18%+（20%-18%）×30÷（30+10）=19.48%≈19.50%",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]